Progress bar for long operations

Reported by: julien-quint Owned by: julien-quint
Priority: blocker Milestone: Obi Beta3
Component: Application Version:
Keywords: Cc:
Blocked By: Blocking:
Time planned: 1d Time remaining: 1d
Time spent: 1d Estimated Number of Hours:
Add Hours to Ticket: Billable?:
Total Hours:

Description

Operations that take time need a progress bar (e.g. exporting to DAISY.)

Change History

comment:1 Changed 11 years ago by julien-quint

We need to kinds of progress bar. One for background operations (rendering waveforms), that appears in the status bar of Obi. When this is going on the user can still use Obi but may decide to wait for the process to be over before doing actual work. The second kind is for blocking operations such as export, where a modal dialog with its own progress bar.

comment:1 Changed 11 years ago by julien-quint

  • Owner changed from somebody to julien-quint

Work is in progress; a progress bar is shown when waveforms are rendered (to be improved) and project is exported.

comment:1 Changed 11 years ago by julien-quint

  • Status changed from new to assigned

comment:1 Changed 11 years ago by julien-quint

  • Status changed from assigned to closed
  • Resolution set to fixed

Fixed in r1984.